|
Milestones
2008
May
7
STP
receives another Best of the Best Award, the plant's
third, and another Top Industry Practice Award, the
plant's seventh, for developing and applying risk
management for maintenance applications. NEI
Best of the Best Award Press Release
2007
September
24
NRG Energy, Inc. and the STP Nuclear Operating Company
apply for a license to build and operate two new units
at the South Texas Project nuclear power plant site.
This is the first license application for a new nuclear
plant in the U.S. in 29 years. NRG
COLA Press Release.
September
17 STP
reports lowest production cost among U.S. nuclear
plants, 1.356 cents per kilowatt-hour in 2006. 2006
Production Cost Press Release.
July
13 The
Nuclear Regulatory Commission approves STP's request
to use risk assessment and management to determine
allowed outage times for many of the systems and components
covered by the plant's Technical Specifications.
April
20 The
low pressure turbines and main generator rotor in
Unit 2 were replaced in 28 days, setting a new world
record.
March
26 STP
completes a second, and consecutive, breaker-to-breaker
production run. Unit 2 operated continuously for 508
days between scheduled refueling outages. Unit
2 B2B Press Release.
February
15
For the third consecutive year, STP led the U.S. in
electricity production by two-reactor facilities.
The plant's total generation in 2006 was 21.37 billion
kilowatt-hours, which set another record for the facility.
STP
Leads U.S. in Production.
2006
October
27 The
low pressure turbines in Unit 1 were replaced in 26.5
days, establishing a new world record.
October
1
STP
completes the first breaker-to-breaker production
run in the plant's history. Unit 1 operated continuously
for 532 days between scheduled refueling outages.
June
1
For
the second year in a row, STP led the U.S. in the
amount of electricity produced by a two-reactor facility.
STP
Again Leads U.S. Press Release.
2005
May
17 STP
wins its sixth Top Industry Practice Award, for a
major plant modification project spanning several
years. NEI
2005 TIP Awards Press Release.
February
11 STP
led all two-unit plants in the country in annual production
in 2004.
2004
August
10
The American Nuclear Society presents
its 2004 Utility Achievement Award to STP and its
2004 Utility Leadership Award to STPNOC President
and CEO Joe Sheppard.
May
14 STP receives
another Best of the Best Award, the plant's second,
and another Top Industry Practice Award, the plant's
fifth, for a precedent-setting repair project praised
as an "exemplary case study in technical project
management under stress." NEI
Best of the Best Award Press Release
2003
May
22 STP
wins another Top Industry Practice Award, the plant's
third in four years and fourth overall, for pioneering
a technological and regulatory breakthrough.
NEI
TIP Awards Press Release
April
7 James
T. Sheppard takes the helm as STPNOC President and CEO.
Mr.
Sheppard, an executive at STP for ten years, previously
held the positions of vice president and assistant to
the president and CEO; vice president, Engineering and
Technical Services; vice president, Business Systems;
assistant to the executive vice president; and general
manager, Licensing.
2002
December
The
four massive steam generators in Unit 2 are replaced
in 65 days.
March
12
STP Unit 1 led all 103 U.S. reactors in generation in
2001, producing 10.8 billion kilowatt-hours of electricity.
The unit also placed eighth in
production among the 433 reactors worldwide. Unit
1 Leads U.S. Press Release
2001
July
25 The South Texas Project
has the lowest average fuel cost, at four-tenths of
a cent per kilowatt-hour, of any power plant in the
U.S. Fuel
Cost Press Release
June
27 A trio of creative employees receives
a U.S. Patent on an award-winning invention used in
reactor maintenance that can improve safety and lower
operating costs at nuclear plants worldwide.
Patent
Award Press Release
May
22 STP receives the industry's Best
of the Best Trophy as well as a Top Industry Practice
Award, the plant's third TIP Award in five years, from
the Nuclear Energy Institute for the "creative
use of high technology to enhance safety and reduce
costs in fuel storage." NEI
Awards Press Release
February
11 Unit 2 surpasses 100
million megawatt-hours of electrical generation since
going online in June 1989.
2000
December
22 STP
exceeds 200 million megawatt-hours in total production
for both units.
June
21 STPNOC President and CEO William
T. Cottle is elected Chairman by the Board of Directors.
Mr. Cottle replaces Founding Chairman Gerald Vaughn,
who held the office since September 1997.
May
The four steam generators in Unit 1 are replaced
in 75 days, setting a new world record.
February
1 STP
and four other nuclear power plants with reactors of
similar design, size and age sign an agreement to share
resources and expertise, and to gain economies of scale
in purchasing and inventories. The other members of
the Strategic Teaming and Resource Sharing (STARS) alliance
are the Callaway, Comanche Peak, Diablo Canyon and Wolf
Creek plants. The Palo Verde plant also subsequently
joined the alliance.
January
1 The Year 2000 date-change has no affect
on plant operations or equipment, successfully concluding
STP's multi-year effort to find and fix all potential
Y2K problems.
1999
November
STP sets a new global benchmark by completing
the ten-year in-service inspection of its second reactor
in three days. The companion refueling outage was finished
in 26 days, another international benchmark.
October
A NASA Mars Mission team visits STP to discuss
the possible use of a small, portable reactor to power
and heat a Mars base. A second NASA/contractor Space
Station team comes to the plant, to benchmark management
practices.
August
The U.S. Department of Agriculture presents
a Conservation Award to STP for its Texas Prairie Wetlands
and Native Grass Restoration projects.
May
STP receives a Top Industry Practice
Award, the plant's second in three years, from the Nuclear
Energy Institute for a machine designed and built by
employees. Stud
Cleaning Machine Press Release
April
STP performs its first
ten-year in-service inspection of a reactor vessel,
and sets a global benchmark by completing the work in
six days and finishing the accompanying refueling outage
in 32 days. 1RE08
Press Release
March
A team of NASA officials and aerospace contractors
working on the International Space Station project visit
STP to learn how plant staff safely handle and hoist
bulky, heavy objects. NASA, DoD Team Press
Release
March
For the second straight year, the area including
STP led the country in the National Audubon Society's
annual Christmas Bird Count.
1998
July
4
The plant surpasses 150 billion megawatt hours of generation
in less than ten years of operations.
150
Billion Kilowatt-hours Press Release.
June
STP
receives the national, annual Powerplant Award from
Power magazine. Power
Press Release
March
The National Audubon Society announces that
a 15-mile-wide area surrounding STP led the U.S. in
the organization's annual Christmas Bird Count.
1997
December
31 STP's two units generated
19.85 billion kWh of electricity in 1997.
December 19
The NRC issues its Systematic Assessment of Licensee
Performance ratings of the South Texas Project, conferring
"Superior" marks in the Maintenance, Operations
and Support categories, and a "Good" rating
in the Engineering category. NRC
Press Release
November 14
The STP Nuclear Operating Company officially assumes
management of STP from Houston Lighting & Power,
completing a nearly two-year transition. STP
Nuclear Operating Company Press Release
October 4
The
seventh refueling of Unit 1 is completed in 21.6 days,
quickest in the units history. The unit was on-line
456 out of a possible 460 days in its 18-month operations
cycle. 1RE07
Press Release
June
STP
places in the top ten percent nationally in low-cost
electricity production. UDI
Press Release
May
STP receives a Top Industry Practice
Award, for outage management, from the Nuclear Energy
Institute. Outage
Management Press Release
March
20 The Texas Prairie Wetlands Project,
a manmade habitat for waterfowl, is officially dedicated
next to STP's main entrance. The Wetlands Project
is the first partnership of its kind between conservation
groups and Gulf Coast industry. Wetlands
Press Release
February
24 Unit
2 sets a new record for the fastest refueling outage
in the U. S., 17.6 days. 2RE05
Press Release
February
12 STP
led all 33 two-unit plants in the U.S. in production
in 1996.
1996
December
31 Units
1 and 2 performed at record levels for the year, together
generating 20.7 billion kilowatt-hours of electricity,
enough for more than one million Texas homes.
For 1996, Unit 2 ranked second in the U.S. and sixth
in the world, while Unit 1 ranked third nationally and
seventh worldwide. Best
Year Press Release
June
13
The combined output of STP's units tops 100
billion kWh since going on-line in 1988.
June 9
Unit 1 sets a new national record for shortest
outage: 22 days 15 hours and 14 minutes. The outage
sets another world record for quickest among four-loop
PWRs. 1RE06
Press Release
May 1
HL&P
and the City of Austin reach an out-of-court settlement.
Austin agrees to drop all litigation against HL&P;
both parties agree to form a separate operating company
to run STP.
The NRC issues its Systematic Assessment of Licensee Performance
ratings for STP, awarding "Superior" marks
in the Maintenance and Support categories, and "Good"
ratings in the Operations and Engineering categories.
1995
December
31
Unit 2 ranks third nationally and tenth globally
in electrical generation by a nuclear plant, despite
a full refueling outage.
November
2 Unit 2 establishes a world record
for the shortest refueling/maintenance outage of a four-loop
pressurized water reactor: 26 days 11 hours 51
minutes.
1994
December 31
For the last six months of 1994, Unit 2 leads
nuclear plants nationwide in amount of electricity generated,
producing more than 5.7 billion kilowatt hours. Unit
1 places second with more than 5.68 billion kWh.
May
22
Unit 2 returns to service.
May
17
NRC approves restart of Unit 2.
March 22
Unit 1 is placed back in service.
February 22
City of Austin files lawsuit against HL&P
to recover fuel costs associated with the year-long
outage at STP.
February 16
NRC Chairman Ivan Selin visits STP and describes
plant, "as well designed and as good a physical
facility as there is in the United States."
February 14
NRC approves restart of Unit 1.
1993
November
Fuel reload of Unit 1 is completed.
October
Steam generator tube inspections finished on
both units.
March
William T. Cottle is named Group Vice President,
Nuclear by HL&P.
February
Both units are taken out of service to resolve
problems with steam-driven auxiliary feedwater pumps.
1992
December
Unit 2 sets a record for most electricity generated
in
a calendar year by any US reactor, 10.8 billion kWh.
September
Unit 1 sets a world record for Westinghouse
reactors for the most electricity generated in a fuel
cycle, 14.5 billion kWh.
June
The combined output of STP's two units tops 50 million
kilowatt hours since they went on-line in 1988.
April
With the refueling of Unit 2, STP completes
the transition
to an 18-month fuel cycle.
1991
January
15 The third refueling/maintenance outage for Unit 1 begins.
All 193 fuel assemblies are removed and inspected. Seventy-six
new assemblies are added as part of the transition
to an 18-month refueling cycle.
1990
December
11 Unit 2 returns to service.
September 28
The first refueling of Unit 2 begins.
June 21 Unit 1 returns
to service.
March 30 Unit 1
enters its second refueling outage.
1989
October 19
The first refueling outage for Unit 1 is completed.
August 4
Unit 1 is refueled for the first time.
June 19
Unit 2 enters commercial operation.
This completes STP's transition from a construction
project to a fully operational electric generating station.
March 28
The NRC grants a full-power license for Unit
2.
March 12
Unit 2 reaches initial criticality.
1988
December
20 Fuel loading of Unit 2 is completed.
December
16 The NRC issues a low-power license
for Unit 2.
August 25
Unit 1 is placed in commercial operation.
March 21 The
Nuclear Regulatory Commission grants a full-power license.
Within 48 hours, power-ascension testing begins.
March 8
Unit 1 reaches initial criticality.
1987
August
22 Fuel
is loaded in Unit 1 and low-power testing begins.
August
21 The NRC issues low-power license
for Unit 1.
January
28 First shipment of nuclear fuel is
received from Westinghouse.
1986
August
29
The
NRC's Atomic Safety and Licensing Board (ASLB) recommends
that STP receive an operating license.
June
18 Concrete work on the Unit 2 dome is completed.
1985
May
30
A settlement of the lawsuit with Brown & Root is
announced. The company agrees to pay STP's owners $750
million for problems encountered during Brown &
Root's tenure at the plant.
February
Work commences on installation of the Unit 1 reactor
vessel internals.
1984
July
Setting of the main control panels for Unit 1 is completed.
The Unit 2 reactor vessel is set and the dome liner
is completed.
1983
August
11 Final
concrete placement for the Unit 1 RCB dome is completed.
July
1 Filling of
the Main Cooling Reservoir commences.
January
6 City of Austin
sues HL&P, charging the company mismanaged construction
of the plant.
1982
February
15
Ebasco Constructors, Inc. named as new constructor.
1981
December
26
Owners commence breach of contract lawsuit against Brown
& Root.
November
4 Brown & Root begins withdrawal
from project after company, owners fail to reach agreement
on constructor scope.
September
24 Brown & Root forecasts project completion
for June 1989 at cost of $4.4 to 4.8 billion.
The forecast is rejected by the owners, who relieve
Brown & Root of engineering responsibility.
Bechtel Energy Corp. named as project's new architect/engineer.
Brown & Root remains as constructor.
1979
August
Steam generators for Unit 1 are set in place.
July
Reactor vessel for Unit 1 is set in place.
1976
April
First permanent concrete poured for Unit I Reactor
Containment Building (RCB) foundation.
1975
December
22 The
NRC issues construction permits for Units 1
and 2.
September
26 The ACRS
writes a letter to the NRC stating that STP can be built
and operated safely.
August
27 The Advisory Committee
on Reactor Safeguards (ACRS) subcommittee meets in Bay
City.
February
7 First pre-hearing
conference and site visit is held by the Nuclear Regulatory
Commission, the successor to AEC.
1974
May
19
An
application for plant construction permits is submitted
to the Atomic Energy Commission (AEC).
1973
November
18
Voters
in Austin approve the City's participation in the South
Texas Project.
August
6 Brown & Root is named as the engineer/constructor
for the project.
June
28 The San Antonio
City Public Service Board signs a participation agreement
to become an owner of STP.
June
6 HL&P and
CPL announce plans at a public meeting in Bay City to
build the South Texas Project nuclear plant in Matagorda
County.
1971
December
6
Houston
Lighting & Power Co., the City of Austin, the City
of San Antonio, and the Central Power and Light Co.
(CPL) initiate a study on the feasibility of constructing
a jointly-owned nuclear plant.

Back
to the Top
|